Skip to menu

BUSINESS

Hazard &risk prevention plan

Business overview
It is a legal system to contribute to preventing industrial accidents and maintaining / promoting worker safety & health and securing fundamental safety by preparing/ submitting a hazard & risk prevention plan, and undergoing safety screening in advance, before installing, relocating, or modifying all construction, machinery, furniture, and facilities directly related to the production process.
Reference [Industrial Safety and Health Act] Article 48
· Non-submission, etc.: A fine of not more than 10millionwon
· Violation of construction stop order, etc.: imprisonment for not more than five years or a penalty of not more than 50 million won

Fee (Ministry of Employment and Labor Notice No. 2013-2)

Move left and right with your hands.
Types Scale Fee (won)
In case of installing and relocating an integrated facilityin 13 major industries A. Electricity contract capacity is less than 50kW
B. Electricity contract capacity is less than 2,000kW
A. Electricity contract capacity is2,000kW or more
84,000
123,000
183,000
In case of expanding, relocating, or changing part of a facility in 13 major industries 67,000
In case of installing or relocating 5 facilities A. Less than 3facilities
B. Less than 6facilities
C. 6facilities or more
44,000
58,000
67,000
In case of changingpart of 5 facilities 36,000

Submittee and when/documents/methods of submission

Q. Who should submit?

A. The business owner of the workplace subject to the submission of the hazard&risk prevention plan

Q. How isitprepared?

A. . It must be prepared by a qualified person for creating hazard & risk prevention plansand with reference to the data provided on the public corporationwebsite

Submission period (15 days before the start of work)
- 15 days before the start of the main facility installation / constructionwork as the time to start the installation/relocation/change of construction machinery, furniture, facilities, etc.
Documents to be submitted
· Application form [Industrial Safety and Health Act Enforcement Rule] Attachment No. 25 Form
· Two copies of the Hazard& Risk Prevention Plan
How to submit
· Submit to: supervisors in the regional headquarter of the public corporation having jurisdiction over the location of the workplace
· Payment of screeningfee: deposit the screening fee to the virtual account provided after submitting the plan
STEP 01
Website of Korea Occupational Safety and Health Agency
www.kosha.or.kr
STEP 02
Business guide
STEP 03
Certification inspection / screening
STEP 04
Screening and verifying hazard &risk prevention plans for manufacturing industries, etc.
STEP 05
Available for download in the archives

Screening and Verifying Procedure for Hazard &Risk Prevention Plans